Terraced sandstone and bushrock retaining walls below a white hinterland home
Case Study

Tallebudgera: 200 Metres of Walls on a Landslide-Hazard Slope

An extremely steep block in the Gold Coast Hinterland, built through a wet year — bushrock and sandstone terraces turned ground that couldn't be used into a garden.

Location
Tallebudgera, Gold Coast Hinterland
Site
Extremely steep, landslide hazard overlay
Built
July 2024 – July 2025
Materials
Bushrock and sandstone block
Wall heights
0.5 m to 1.5 m
Total wall length
Approximately 200 metres
The site

A slope that couldn't be used

This block in Tallebudgera, in the Gold Coast Hinterland, was one of the steepest sites we've worked on. It carries a landslide hazard overlay, and the ground falls away sharply from the house.

Because the entire property sat on that gradient, most of it was effectively unusable — there was very little level ground to garden, sit or move around on.

The brief

Better looks, usable ground

The homeowner wanted two things: to improve how the site looked, and to create genuinely usable outdoor areas out of a block that had none.

That meant building structure into the slope — walls that hold the ground, step with the fall and form level terraces along the way.

What we built

Bushrock, sandstone and a lot of patience

We built approximately 200 metres of retaining walls across the property. The walls step down the slope in a variety of heights, from 0.5 metres to 1.5 metres, so the terraces follow the natural fall of the land rather than fighting it.

The build combines bushrock boulders with sandstone block. Bushrock does the heavier structural work on the steeper sections, while sandstone block gives clean, consistent lines for the walls and steps closer to the house.

200 m
of retaining wall built
0.5–1.5 m
wall heights
12 months
on site

Building through the weather

A wet year on a steep site

Construction commenced in July 2024 and was completed in July 2025 — a full year on site, largely because of the weather.

Wet weather delays were constant throughout the build. On a slope this steep, saturated ground has to dry out before it can be safely worked, so the program was sequenced around the rain rather than the other way around.

The build

Tallebudgera, in pictures

Terraced sandstone walls and garden beds below the house
Terraced sandstone walls and garden beds below the house
Chiselled sandstone steps leading up to the house
Chiselled sandstone steps leading up to the house
Sandstone stairs stepping through the planted terraces
Sandstone stairs stepping through the planted terraces
Bushrock boulder terracing beside the sandstone steps
Bushrock boulder terracing beside the sandstone steps
Sandstone steps and tiered retaining wall with landscaped garden

Let's Build Something That Belongs There.

Tell us about your property and we'll arrange an on-site assessment to discuss the right solution for your project.

admin@rocksmithconstruction.com.au
Get a Quote

Request an On-Site Assessment

Tell us about your property. We'll be in touch to arrange an obligation-free on-site assessment and discuss the right retaining wall solution for your project.

Brisbane Southside & South East Queensland

Open in Google Maps

Uploaded photos are stored privately — no public URL, so access follows your app's permissions.